Lesson 22 · Keep it current

Handle a delay

Procedure · Grid · Timeline
01In the Grid, double-click the late task’s Duration, press Ctrl+A, type the new length and press Enter.
02Its Finish date moves out, and every task that depends on it moves too.
03Open Timeline to see the knock-on effect.

Fig 22.1Recording, 11 s. Adding a day to a task and watching the next one shift.

Click to play full size
NoteThen check the end date

Scroll to the end and make sure the final milestone still lands on 15 January 2027. Shortening the task again pulls everything back.