Planner Field GuideChapter 02 · Work a taskLesson 09 / 31
Lesson 09 · Work a task

Set % complete

Fig 09.1Recording, 9 s. Setting a task to 40% complete.

Click to play full size
Procedure · Details pane · % Complete
01In the details pane, click % Complete.
02Type a number, like 40.
03The phase rows above it update on their own.
09Chapter 02 · Work a task
← Lesson 08Lesson 10 →