Turn a task into a milestone

Procedure · Details pane · Duration
01In the details pane, click Duration.
02Press Ctrl+A, type 0 days and press Enter.
03On the Timeline it now shows as a diamond. The clip stops at the duration change; you can see the diamond at the end of step 18.

Fig 10.1Recording, 12 s. Changing a task’s duration to 0 days.

Click to play full size
CautionSelect the old value first

Select the old value first. Typing straight over “1 day” turns it into “10 days”.