Fig 19.1Recording, 21 s. Changing a task’s duration and start date.
Click to play full size3 days. The Finish date moves out.Typing a date into Start doesn’t stick, so pick it on the calendar. Picking a Start also adds a “start no earlier than” constraint. The picker shows a Remove constraint button if you don’t want it.
Effort hours follow the duration: 2 days is 16 h, 3 days is 24 h.