Lesson 20 · Keep it current

Mark a task complete

Procedure · Grid · Board · Charts
01Click the circle next to the task name, in the Grid or the details pane.
02Planner sets it to 100%, moves the remaining effort to completed and strikes the row through.
03On the Board it shows under Completed, and Charts takes one off the tasks-left count.

Fig 20.1Recording, 17 s. Completing a task, then checking the Board and Charts.

Click to play full size
NoteIt stays in its bucket

Completing a task doesn’t move it to Done. In the clip it sits in In progress at 100%. If you use the Done column, move the card yourself.

NoteChanged your mind?

Untick the circle or type the old % back in.