Lesson 27 · Run the project

Status, bucket and checklist are separate

Fig 27.1Recording, 13 s. Ticking a checklist item. The count goes up, the % doesn’t.

Click to play full size
Procedure · Details pane
01Status is the circle and % Complete: how finished the task is.
02Bucket is the column, Backlog through Done: where it is in the process.
03Checklist is a to-do list inside the task. Ticking an item changes the count (1/4 to 2/4) but not the %.
NoteRule of thumb

None of these updates the others. When work moves on, update the % and move the bucket yourself. Use the checklist for the small steps.