Follow one task from start to finish

Procedure · Details pane · Board
01Open the task. Check the assignee and the dates.
02Blocked: bucket to Waiting on others, plus a Blocked: note saying what you’re waiting for.
03Back on: bucket to In progress, and set the % as work happens (50% here).
04Checking: bucket to Review / Verify.
05Done: tick the circle (100%), then move the bucket to Done.

Fig 28.1Recording, 54 s. One task going from blocked to in progress, review and done.

Click to play full size
NoteTip

When a blocker clears, update or delete the Blocked: note. I left it in the clip so you can see it the whole way through.